Axtell
Creek
Selection
of Sites for Action
(Version
I: March, 2003)
|
hit the back button to
return to this page from any links
General background on the approach used for this process and information
on the Axtell Creek subwatershed can be found in the Watershed
Management Plan (WMP) Overview and on the Scoring
Table webpage. This site selection process started with a review of
the scoring results for the stream corridor
of the creek. Scoring was based upon ten physical, observable parameters
with a ranking of 0-3 for each, resulting in a maximum of 30 total points
for each stretch. High scores were reflective of "good" conditions. Discussions
focused not only upon these stream corridor conditions, but also on any
upland opportunities that would reduce direct stormwater contributions
to the creek. Periodic flood damage at the Crosstown Ponds provides incentive
for upland approaches that reduce stormwater volumes reaching this area.
Consideration of suitable BMP options for conditions at sites of concern
included consideration of: the greatest community benefit and a "maximum
return" on any investment in improvements. Five of the 6 numbered sites
scored below 20. The Stretch Property
Summaries Table, provides each stretch by: number, location, description
and score. In the approach used below, site numbers run sequentially from
the source of the watercourse to the mouth of the creek. Numbers in the
following discussion summaries correspond to the same stream segment numbers
found in the summaries table. The BMP
Implementation Table (PDF format, will open in new
browser window) provides a summary of proposed BMPs for each stretch
and their associated costs. (Links within that table provide additional
cost information for selected stretches). Please refer to the Axtell
Creek Subwatershed Virtual Tour for additional supportive information
on flow path and locations described in the following text.
In general, the Axtell Creek component of the plan calls for:
- protection of the headwaters and wetlands,
- bank reshaping and vegetation restoration along some stretches,
- a slight expansion of the floodplain,
- alterations to current maintenance operations,
- an educational walking tour with signage,
- south pond inlet and outlet small quantity localized dredging,
- alteration around the south pond perimeter with regrading and revegetation,
- restorative work around the mouth of the creek in conjunction with
the redevelopment plans for Upjohn Park, and
- exploration of the need to install a flood gate at or near the mouth.
Axtell Creek has distinct section characteristics: the upper, headwaters
reaches are in what technically is termed a lotic (flowing water) condition
(stretches 1-4), while the lower reaches are in more of a lentic (standing
water) condition (stretches 5-6).
Stretch #1 (28 points)
Description
A very high score resulted for this stretch, as it is comprised of
the City of Kalamazoo Well Field #4, which is protected from development.
Wooded wetlands and open water dominate the stretch. Artesian flows and
pressure relief flows from City well heads contribute to the base flow
of the creek. The area is surrounded by higher elevations with medium-density
commercial and residential development. Mapped
natural areas, including the Kleinstuck Preserve, are in close proximity
to this stretch.
Impacts
This stretch is currently impacted by two stormwater outfalls and
an apparent illicit discharge of swimming pool water. The area has considerable
invasive plant species present, and should be managed as a unique natural
feature in an urban setting. Surface and some bank erosion within the
site may be contributing to the need for sediment removal from the culvert
under Maple Street which appears to have restricted flow.
Recommendations
It has been recognized as a protection goal of this plan to provide
both wetland and wellhead protection for the headwaters from any sources
of potential or actual contamination.
Stretch #2 (16 points)
Description
The creek flows along Crosstown Parkway and the Maple Street School
ball fields from Maple Street to Howard Street in Stretch #2.
Impacts
The original channel has been altered as evident by old aerial photographs
and the current 90-degree bend at the corner of Crosstown Parkway and
Maple Street. Virtually no natural meanders remain in this reach. Close
proximity of the channel to Crosstown Parkway, in this and the remaining
stretches, allows litter, debris, oils and soils to enter the watercourse.
The area has limited riparian vegetation, which has been slightly impacted
by fence reconstruction operations at Maple Street School. Bank erosion,
slow flow rates and natural vegetative decay have contributed sediment
and nutrients that, over time, created an organic-rich, thick substrate
with little cobble or gravel. However, fish have been observed in this
stretch.
Recommendations
The Girls Scouts of Southwest Michigan have recently purchased an
adjacent property (on the east side of Crosstown Parkway and south of
Maple Street), which is proposed to be utilized for hiking and nature
education. Collaboration with their activities in order to maintain and/or
enhance all possible local green space is recommended.
The Maple Street School football field is scheduled for
rebuilding in 2003 with bond monies already set aside. Use of excavated
soil from on-site (the wetland area) would reduce costs by not needing
to import soils. This replacement operation has turned into an excellent
restoration opportunity as described below.
It is recommended that the stream course be restored to
a moderate, natural meander and include a created wetlands component from
the middle area of the reach to Howard Street. A portion of the ball field
near the creek has always caused a maintenance problem because it usually
wet. The proposed created wetland, restorative plantings and educational
features are welcome additions from the perspectives expressed by the
school principal, facilities manager and the superintendent. Agreed upon
future meetings will move these activities forward to the implementation
stage in 2003. Predominantly native vegetation, suitable to these conditions,
should be used as planting materials. The City of Kalamazoo could restore
some of this vegetation in the street right-of-way areas, especially the
northwest corner of Howard Street and Crosstown Parkway. Plans will incorporate
and encourage middle school student involvement in this educational restoration
project and include materials for a self-guided tour of the creek.
Stretch #3 (11 points)
Description
Passing under Howard Street, the creek flows northeast along the west
side of Crosstown Parkway. This area is visible daily to pedestrian and
vehicular traffic.
Impacts
Current landscaping practices along this stretch (mowing/trimming
vegetation to the creek edge) do not allow any riparian vegetation to
become established.
Recommendations
An educational component, such as the walking tour of urban stream
stewardship alluded to in the previous stretch, should be included and
continued in any restoration along this stretch. Most riparian landowners
in this stretch are willing to institute changes. Currently the WildOnes
and Kalamazoo Greenspaces are working with Benefiel et al., law offices
to develop a multi-dimensional planting plan for the corner surrounding
their offices. A City of Kalamazoo representative met with Crosstown Parkway
Senior Apartments management to discuss an overall strategy for this segment
and options for their participation. The walking tour would be a fine
amenity for their residents to use. The WMP recommends creation of a coalition
of committee members to assist apartment management and other riparian
property owners to implement consistent improvements. Creation of an expanded
floodplain from the law offices (Howard Street) to Paris Cleaners, even
though relatively small in size, could become part of these restoration
efforts.
Stretch #4 (17 points)
Description
Stretch #4 consists of a small section along a paved parking area
behind Paris Cleaners and an office building. Axtell Creek Park is located
on the opposite bank. A narrow strip of wooded vegetation shades the water
and provides some habitat.
Impacts
Several storm sewers (drains) empty into this area. Parking areas
in riparian areas allow overland flow to contribute storm water directly
to the creek, accelerating erosion.
Recommendations
Planting of understory vegetation and a diversion of parking lot storm
water to detention areas (if space allows) may alleviate this situation.
Infiltration swales and the elimination of "sluices" are recommended.
Owners of the Paris Cleaners will need to be willing to address the recommended
alterations. Upland educational efforts within the residential neighborhoods
that contribute flow to these points will be undertaken to reduce the
volume of storm water flowing to the creek. Areas suitable for grassed
swales and other physical BMPs will continue through cooperative efforts
between the committee, the city and the neighborhood.
Stretch #5 (1 point)
Description
Stretch #5 encompasses the channel along the National City parking
lot and the Crosstown Ponds.
Impacts
Severe erosion and development issues plague this stretch. The bank
drive-thru/parking lot is on the verge of collapse due to the south creek
bank eroding and undercutting this section. The lot is oversized for its
current use based upon multiple observations of vehicles in the lot throughout
different seasons and different times of the day. The north bank of the
watercourse is similarly impacted. The banks of the south pond (most upstream
of the three Crosstown Ponds) are severely eroded, as no vegetative buffer
exists. Bank erosion from small but frequent fluctuating water levels,
large storm water inputs and excessive waterfowl populations contribute
high nutrient loads to this pond. Sediment retention capacity and limited
storm water detention do still exist. (The south pond is shallow compared
to the other two.) The city, as part of its current storm water infrastructure
evaluation program expects to verify that sediments need to be dredged
from the inlet and outlet of the pond.
Recommendations
The recommendation is to work with National City Bank (property owner)
and evaluate if there may be a desire and room for cutting back the lot
and installing vegetated detention swales and vegetative buffers. An extremely
visible area, the park is surrounded by major thoroughfares and consistently
high traffic volumes. The land use surrounding the ponds is a mixture
of commercial, residential and park land. Recreational use of the park
land is limited by excessive amounts of waterfowl droppings and, probably,
degraded aesthetics. Restoration of the habitat quality of the area is
expected to reduce waterfowl use, enhance aesthetics and increase the
recreational value. Use of the area by the public and its visibility to
traffic makes it an excellent candidate for urban watershed stewardship
education. Additionally, as a gateway to the southern neighborhoods of
Downtown Kalamazoo, it should serve as a showcase of the city's commitment
to economic and environmental harmony. Following the release of a study
of the ponds by Conestoga-Rovers & Associates (June 2002), and participation
in this watershed management planning process, the city is moving forward
with budget recommendations for the implementation of improvements, including
additional BMPs in the area. These improvements began with a change in
mowing operations to create a 5-10 foot wide "no-mow" zone around the
banks of the south pond in June 2002.
The plan targets the south pond initially and leaves the
other two ponds for future considerations. Recommended first steps include:
- dredging the inlet and outlet of the south pond,
- installing a sediment trap at the inlet,
- reshaping/regrading the banks,
- instituting a community-based replanting effort with native varieties
of wet-edge and emergent vegetation around most of the pond, and
- keeping one or two areas at the pond's water edge accessible to
the public.
Additional targets include:
- a long-term recommendation to construct two simple elevated or floating
structures for low impact public access to the water,
- restrictions of nuisance waterfowl,
- installation of signs as part of a community education effort,
- turning the park into a key demonstration site, and
- the development of a maintenance plan to routinely remove litter
from all outlets, especially the outlet of the third pond, where it
accumulates.
Periodic flooding in this location is associated with backflowing
of water from Portage Creek and the lmited infiltration capacity of the
three ponds and surrounding areas.
Stretch #6 (12 points)
Description
Axtell Creek is piped underground for a considerable distance from the
outlet of the third pond to the intersection of John Street and Crosstown
Parkway. The watercourse then flows behind a City of Kalamazoo property
to its convergence with Portage Creek at Upjohn Park. A narrow strip of
mature trees lines the banks with some scrub vegetation as understory.
Impacts
Severe erosion was noted at the culvert where the creek emerges. Water
clarity is poor, as this stretch appears to receive considerable nutrient
and sediment loading from impervious land uses that dominate the drainage
area. Flow is relatively stagnant during dry weather periods. During large
storm events, flows from Portage Creek back up into Axtell Creek (photo
1), causing flooding, which extends to the Crosstown Ponds (photo 2).

Both photos taken
August 22, 2001. Photo 1 looking from Upjohn Park south toward Portage
Creek just downstream of the confluence with Axtell Creek. Crosstown Parkway
is on the right. Photo 2 is looking southeast across Park Street to the
south pond.
Recommendations
Addressing storm water inputs and imperviousness in the lower reaches
of Portage Creek and in the highly urbanized areas of the Axtell Creek
Subwatershed is a priority. The area along the southeast corner of the
convergence of the two creeks is proposed for a created wetlands project
by the City of Kalamazoo. Recommendations are to:
- alterations of mowing practices,
- potentail diversion of parking lot runoff to the created wetland and/or
use of permeable paving materials at the adjacaent ciyt property along
Crosstown Parkway,
- repair erosion around the culvert at the beginning of the stretch
- explore potential for opening channel sections that are now piped
(one alternative is to consider leaving channel bottom exposed and closing
sides and top only),
- study the feasibility of installing one or a series of flood control
structures (one or two on Portage Creek upstream from Axtell and one
on Axtell near the mouth), and
- bank shaping and stabilization with newly planted native vegetation
as part of the Upjohn Park renovation.
back to top
|